Valmet Received EUR 40 Million Order to Supply a Hot Water Plant to Goteborg Energi in Sweden

Valmet Received EUR 40 Million Order to Supply a Hot Water Plant to Goteborg Energi in Sweden

Specifications:

Name:

Valmet Received EUR 40 Million Order to Supply a Hot Water Plant to Goteborg Energi in Sweden

Location:

Sweden

Company:

Valmet

Estimated Cost:

EUR 40 Million

Source:

www.valmet.com

Introduction:

Valmet will supply a complete plant for the production of district heat to Göteborg Energi AB in Gothenburg, Sweden. With the new hot water plant, fossil CO2 emissions will be reduced by 25,000 tons per year.

Features:

The new boiler plant will replace two old boilers originally designed for oil and coal but converted to run on wood pellets in 2003. Demolition of the existing plant will start in April 2021, and the new plant will be started up in December 2021.

The new boiler will be 25 percent larger than the two old ones combined. It will also have a longer operating season. Since the number of operating hours on pellets will increase, the use of natural gas will decrease. The ash from the combustion will be returned to the forest.

Valmet will demolish the existing boiler plant and build the new one, including fuel preparation, ash handling and flue gas cleaning systems. The delivery also includes the installation, start-up and predictive maintenance for the boiler plant. The boiler will have a fuel capacity of 130 MW and will be based on Valmet’s technology for large pellet-fired boilers.

The order is included in Valmet’s orders received of the second quarter 2020. The value of an order of this size and delivery scope is typically above EUR 40 million.