Siemens Received €790 Million Substation Contract From Qatar General Water

Latest Industry Projects

Siemens received €790 Million substation contract from Qatar General Water & Electricity Corporation (KAHRAMAA)

Siemens received €790 Million substation contract from Qatar General Water & Electricity Corporation (KAHRAMAA)

Introduction:

State-owned utility Qatar General Water & Electricity Corporation (KAHRAMAA) has awarded Siemens the largest contract to-date in Qatar for the expansion of the country's power transmission network.

Features:

Siemens will deliver 35 turnkey super and primary substations for Phase 13 of the Qatar Power Transmission System Expansion project. This marks a significant milestone for Siemens, which has maintained involvement in every stage of the project since Phase 4. Completion is scheduled in two years' time.

Siemens will be responsible for the design, engineering, supply, installation, and commissioning of the substations for the 400-kilovolt (kV), 220-kV, 132-kV, 66-kV, and 11-kV voltage levels, including gas-insulated switchgear, transformers, and control and protection equipment. As part of this contract, an existing 'super substation' – one that allows multiple voltage settings – in Doha will be upgraded with new 400kV/200kV gas-insulated switchgear and associated equipment, before connecting to the grid. Another substation will be used to meet rising demand for electricity in Al Jahhaniya and surrounding area, including temporary power feed to Rayyan Stadium, one of the venues for the upcoming world soccer championship.

Since the upgrade program started in 2005, Siemens has installed more than 120 substations and approximately 1,500 kilometers of high-voltage cable. With this new order intake, our completed and under execution projects with KAHRAMAA total nearly EUR2.5 billion.

In addition to Phase 13, Siemens also received a second order from KAHRAMAA to supply and install more than 2,170 medium-voltage switchgear boards. The 8DJH switchgear will be used as ring main units (RMU) in the 11 kV distribution network. RMUs protect, for example, transformers connected to the grid against overloads and short-circuits, ensuring a reliable power supply. The switchgear will be manufactured in Frankfurt, with the first units expected to go into operation by end-2017. The order is valued at roughly EUR27 million.

Specifications:

Name Siemens
Order Received From Qatar General Water & Electricity Corporation (KAHRAMAA)
Type Substation Contract
Estimated Cost EUR790 Million

 

Source: siemens.com 

Other Projects